New Ross Flood Alleviation scheme

New Ross Flood Defence

Date: 2017-2018

Project details:

This project involved the erection of flood defences along the river Barrow in New Ross Co. Wexford the project involved the following

Construction of R.C. flood walls with stone cladding

Construction of glass flood walls

Demolish and reconstruct walls at O Hanrahans bridge

Construction of pillars for demountable flood barriers

Construction of flood embankments with rock armour protection

Modify existing pump station in Rosbercon

New Ross Flood Alleviation scheme

New Ross Flood Defence

Date: 2017-2018

Project details:

This project involved the erection of flood defences along the river Barrow in New Ross Co. Wexford the project involved the following

Construction of R.C. flood walls with stone cladding

Construction of glass flood walls

Demolish and reconstruct walls at O Hanrahans bridge

Construction of pillars for demountable flood barriers

Construction of flood embankments with rock armour protection

Modify existing pump station in Rosbercon

New Ross.jpg
new ross.jpg
  Capping beam on top of sheetpiles

Capping beam on top of sheetpiles

IMG_0322.jpg
IMG_2596.JPG
IMG_0350.jpg
IMG_0643.JPEG
IMG_0352.jpg
IMG_0194.jpg
IMG_4877.JPG
IMG_4882.JPG
IMG_0342.jpg
IMG_2504.JPG
IMG_5576.JPG
IMG_5429.JPG

MJS Civil Engineering
Kilday Farm
Kilday
Newtownmountkennedy
Co Wicklow
(01) 2011895
hello@mjscivilengineering.ie