![IMG_0429.jpg](https://images.squarespace-cdn.com/content/v1/57f5256ed482e9ea7f424935/1570117761673-XTWOWXXAH64WCZ3QBQ14/IMG_0429.jpg)
![IMG_0708.jpg](https://images.squarespace-cdn.com/content/v1/57f5256ed482e9ea7f424935/1570117837835-GUWQWVGWEFKV979R4XTH/IMG_0708.jpg)
![IMG_0723.jpg](https://images.squarespace-cdn.com/content/v1/57f5256ed482e9ea7f424935/1570117929206-C39HAV8B4N7ET9BYL5T5/IMG_0723.jpg)
![IMG_0788.jpg](https://images.squarespace-cdn.com/content/v1/57f5256ed482e9ea7f424935/1570117996531-H3T2WV58TAYAAFYPS1B4/IMG_0788.jpg)
![IMG_0790.jpg](https://images.squarespace-cdn.com/content/v1/57f5256ed482e9ea7f424935/1570118137286-E0MSAV4SFKV8DEL0APJF/IMG_0790.jpg)
![IMG_0802.jpg](https://images.squarespace-cdn.com/content/v1/57f5256ed482e9ea7f424935/1570118154387-NLA0YF87NUWJQXC6NK5M/IMG_0802.jpg)
![IMG_0813.jpg](https://images.squarespace-cdn.com/content/v1/57f5256ed482e9ea7f424935/1570118164299-U7CSLX8THYUZCTLOE4LX/IMG_0813.jpg)
![IMG_1133.jpg](https://images.squarespace-cdn.com/content/v1/57f5256ed482e9ea7f424935/1570118174021-XD8DNZBA0W79R307XK54/IMG_1133.jpg)
Your Custom Text Here
Client- Waterford City &County Council
PSDP- MJS civil engineering
Works were carried out between July and September 2019
Scope of works
Construction of 900 mm outfall pipe from Tournore Dungarvan
Works
Laying of 40 m of 900 mm concrete pipe including a road crossing of the R675 Clonea road - construction of two new manholes and the demolition and reconstruction of a section of existing flood wall
Laying of 170 m of 900 mm HDPE pipe across mudflats to sea including the construction of a continuous concrete arch over pipe
The construction of a end block with flap valve and rock armor protection fitted with a flap valve
Client- Waterford City &County Council
PSDP- MJS civil engineering
Works were carried out between July and September 2019
Scope of works
Construction of 900 mm outfall pipe from Tournore Dungarvan
Works
Laying of 40 m of 900 mm concrete pipe including a road crossing of the R675 Clonea road - construction of two new manholes and the demolition and reconstruction of a section of existing flood wall
Laying of 170 m of 900 mm HDPE pipe across mudflats to sea including the construction of a continuous concrete arch over pipe
The construction of a end block with flap valve and rock armor protection fitted with a flap valve